Name and Location
of Project
Client
Value
($ 000 000)
Date
Project Details
Agalar Harbour, Pier Construction
MERSIN
(80% of KC JV)
MSB
34.4
2000 - 03
470
13 400
58 000
m
m
m3
Pier
Steel pipe piles (966 ea, 1 200 mm dia.)
R/f concrete
Alapli Harbour
ZONGULDAK
DLH
6.4
1995 - 05
92 000
121
801 545
m3
t
t
Concrete
Steel
Rockfill
Harbour Construction
CANAKKALE
DLH
11.5
1995 - 99
6 640
208 000
36 000
t
t
m3
Steel pipe pile
Rockfill
Concrete
Harbour Extension
RIZE
DLH
9.6
1990 - 94
793 000
36 000
17 000
t
m2
m3
Rockfill
Concrete pavement
Concrete blocks
Dock Construction
ANTALYA
DLH
14.3
1988 - 92
126 000
736 000
m3
t
30 t Pell - Mell concrete blocks
Rockfill
Breakwater & Pier Construction
Yenikapi, ISTANBUL
Municipality
14.1
1987 - 89
3 483 000
600
t
m
Rockfill
Pier on piles
Harbour Extention
TRABZON - MERSIN
DLH
15.3
1985 - 90
2 434 000
254 000
62 000
t
m2
m3
Rockfill
Concrete pavement
Concrete blocks
Pier Construction
Golcuk, IZMIT
MKE
12.5
1971 - 74
16 400
m Concrete piling
111.2